STEEL STRUCTURES & ENGINEERING
PRODUCTION

Fabrication

From material preparation to fabrication, we turn project details into steel components.

PROJECT

Engineering may take approximately 10–15 days. Following approval:

  • Material orders are placed.
  • Single-part drawings are issued, including drilling and cutting preparations; fabrication drawings are prepared.
  • Erection drawings are prepared.

MATERIALS

After the contract is signed:

  • Material lists are extracted from the 3D model and orders are placed.
  • Once procured, materials are sent for abrasive blast cleaning.
  • After Sa 2½ blast cleaning, shop primer is applied at 15–20 microns to protect the surface before workshop delivery.
  • This stage may take approximately 10–15 days.

PREPARATION

The work programme is issued to the relevant teams.

  • Plate and section cutting lists are prepared.

PRODUCTION

Plates and sections are procured according to the lists.

  • Holes are drilled.
  • Columns, beams and bracing connections are fabricated in the scheduled order.

Illustrative images representing production processes.